Products used:
Guardian-WF
Freedomtuff® 6600 Mvr Primer
Freedomtuff® 2243 Cr Polyurea
Freedomtuff®4200 Aliphatic Top Coat
Project description: In october of 2014 kaiser permanente in baldwin park, california would need to specify a waterproofing membrane for a 32,000 sq.Ft. Reflection pond that was leaking into the lower rooms of the hospital. In addition to waterproofing there were upgrades including lighting and new drains that were being added to the pond. Since the pond was only going to be drained once and the timeline was near the “rainy” season in southern california consideration of project delays had to be considered. Kaiser’s design firm who had worked with freedom chemical on the hollywood sunset ave water feature selected the freedomtuff ® products to do the job.
Application: The pond was drained and the existing coating was removed by shotblasting. Surface profile was achieved to meet freedom spec. Since moisture vapor and rain was of consideration 16 mils of freedomtuff® 6600 mvr was applied. Freedomtuff® 2243 cr was applied at 120 mils. Freedomtuff® 4200 aliphatic top coat was color matched to resemble the color of the glass on the building and applied to the side walls of the pond to achieve the desired aesthetics.
Results: By electing to go with the freedomtuff® 6600 mvr they were able to keep constant work flow even though rain did become a factor. Ft-2243 cr was selected to hold up against the cleaning solutions that are being used in the pond. The waterproofing was achieved as well as considerations for aesthetics. The end result also left a very easy to clean surface.
Gallery
The FreedomTuff® product line is a revelation of what Polyureas, Polyurethanes, Polyaspartics and Epoxies are about. When so many products have been “made” for maximum impact, at Freedom® Chemical Corporation we’ve been content to let our products speak quietly. No need to shout when you have something special to say.
Recent Case Studies & Applications
Westfield
Contractor: JP Rodriquez
Job description: 24 Hour Fitness pool deck and sports court
Fertizona – Buckeye, AZ
Contractor: Gamez Lining Systems – Carlos Gamez
Job description: Fertilizer offloading station – Containment
2Cal Tower
Client: CIM Group
Sub-Contractor: Innovative Painting & Waterproofing
Us Department of Interiors
Contractor: Protech Coatings
Job description: Hoover dam parking structure
University of Arizona Tucson
Job description: 36,000 sq.ft. Elevated deck over occupied space
Westfield
Contractor: Angelus Waterproofing
Job description: Underground tunnel for vehicular traffic